Water Systems Upgrades
Federal contribution
$1.2M
$1,207,048
Federal share40%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Vianney
- Construction start
- May 16, 2022(actual)
- Construction end
- Nov 17, 2022(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 13, 2022
- Construction end6 weeks earlyforecast Dec 30, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56459 in the federal list. How to read these figures.