Back to projects

Water Systems Upgrades

Saint-Vianney, Quebec

completeWastewaterGIS
Federal contribution
$1.2M
$1,207,048
Federal share40%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Vianney
Construction start
May 16, 2022(actual)
Construction end
Nov 17, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 13, 2022
  • Construction end6 weeks earlyforecast Dec 30, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56459 in the federal list. How to read these figures.