Water Systems Upgrades
Federal contribution
$2.0M
$1,999,396
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023202420252026
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- mont-saint-hilaire
- Construction start
- May 6, 2022(actual)
- Construction end
- Dec 5, 2025(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 21, 2022
Also in Mont-Saint-Hilaire
- Resurfacing Highway 116 in Mont-St-Hilaire$1.5M
- Program for the renewal of drinking water and wastewater pipes$1.3M
- Program for the renewal of drinking water and wastewater pipes$786.9K
- Rehabilitation of Ozias-Leduc multisport park in Mont-Saint-Hilaire$661.5K
- Program for the renewal of drinking water and wastewater pipes$420.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56468 in the federal list. How to read these figures.