Water Systems Upgrades
Saint-Hubert-de-Rivière-du-Loup, Quebec
Federal contribution
$322,340
Federal share40%
of $805.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Hubert-de-Rivière-du-Loup
- Construction start
- Jun 19, 2023(actual)
- Construction end
- Sep 27, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 6, 2022
- Construction end13 months lateforecast Aug 26, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56470 in the federal list. How to read these figures.