Water Systems Upgrades

Saint-Hubert-de-Rivière-du-Loup, Quebec

completeWastewaterGIS
Federal contribution
$322,340
Federal share40%

of $805.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 19, 2023(actual)
Construction end
Sep 27, 2023(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 6, 2022
  • Construction end13 months lateforecast Aug 26, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56470 in the federal list. How to read these figures.