Back to projects

Drinking Water - Implementation of Manganese Treatment System

Saint-Gilles, Quebec

completeDrinking WaterGIS
Federal contribution
$703,541
Federal share40%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Gilles
Construction start
Sep 27, 2021(actual)
Construction end
May 31, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 21, 2021
  • Construction end2 months lateforecast Mar 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56482 in the federal list. How to read these figures.