Water Systems Upgrades

Paspébiac, Quebec

completeWastewaterGIS
Federal contribution
$1.8M
$1,795,212
Federal share40%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 9, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Paspébiac
Construction start
Jun 7, 2022(actual)
Construction end
Sep 11, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2022
  • Construction end8 weeks lateforecast Jul 15, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56486 in the federal list. How to read these figures.