Water System Upgrades

Eastman, Quebec

completeDrinking WaterGIS
Federal contribution
$436,713
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Municipality of Eastman
Construction start
Jun 20, 2022(actual)
Construction end
Sep 10, 2023(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 4, 2022
  • Construction end12 months lateforecast Sep 7, 2022