Back to projects

Water System Upgrades

Notre-Dame-de-l'Île-Perrot, Quebec

completeDrinking WaterGIS
Federal contribution
$796,776
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 1, 2020(actual)
Construction end
Jul 30, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 29, 2020
  • Construction end2 weeks earlyforecast Aug 15, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56496 in the federal list. How to read these figures.