Water Systems Upgrades
Federal contribution
$464,586
Federal share40%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Sainte-Anne-de-Sorel
- Construction start
- Jun 30, 2020(actual)
- Construction end
- Jul 13, 2021(actual)
Against the original forecast
- Construction start2 months earlyforecast Sep 2, 2020
- Construction end6 weeks lateforecast May 31, 2021