Back to projects

Water Systems Upgrades

Sainte-Anne-de-Sorel, Quebec

completeWastewaterGIS
Federal contribution
$464,586
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Sainte-Anne-de-Sorel
Construction start
Jun 30, 2020(actual)
Construction end
Jul 13, 2021(actual)

Against the original forecast

  • Construction start2 months earlyforecast Sep 2, 2020
  • Construction end6 weeks lateforecast May 31, 2021

Also in Sainte-Anne-de-Sorel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56498 in the federal list. How to read these figures.