Water Systems Upgrades

Richmond, Quebec

completeWastewaterGIS
Federal contribution
$642,930
Federal share40%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Richmond
Construction start
Jun 15, 2021(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start2 months earlyforecast Aug 23, 2021
  • Construction end2 months lateforecast Aug 31, 2022