Water Systems Upgrades

Saint-Isidore-de-Clifton, Quebec

completeDrinking WaterGIS
Federal contribution
$273,900
Federal share40%

of $684.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Isidore-de-Clifton
Construction start
Sep 26, 2022(actual)
Construction end
Jul 31, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2022
  • Construction end7 months lateforecast Dec 31, 2022