Back to projects

Water Systems Upgrades

Lac-Brome, Quebec

completeWastewaterGIS
Federal contribution
$954,065
Federal share40%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022202320242025
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Lac-Brome
Construction start
Aug 2, 2021(actual)
Construction end
Dec 1, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 14, 2021
  • Construction end4 weeks earlyforecast Dec 31, 2024

Also in Lac-Brome

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56508 in the federal list. How to read these figures.