Water Systems Upgrades
Federal contribution
$954,065
Federal share40%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Lac-Brome
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Dec 1, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 14, 2021
- Construction end4 weeks earlyforecast Dec 31, 2024
Also in Lac-Brome
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56508 in the federal list. How to read these figures.