Water and Sewer Main Extension (Morin and Deslauriers Roads) and Pumping Station Relocation (Morin Road)
Federal contribution
$636,000
Federal share40%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021202220232024
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Liboire
- Construction start
- Oct 17, 2022(actual)
- Construction end
- Mar 29, 2024(actual)
Against the original forecast
- Construction start15 months lateforecast Jul 15, 2021
- Construction end2.2 years lateforecast Dec 31, 2021
Also in Saint-Liboire
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56510 in the federal list. How to read these figures.