Water System Upgrade

Saint-Christophe-d'Arthabaska, Quebec

completeDrinking WaterGIS
Federal contribution
$395,846
Federal share40%

of $989.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Oct 28, 2020(actual)
Construction end
Jun 6, 2022(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 5, 2020
  • Construction end18 months lateforecast Dec 15, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56536 in the federal list. How to read these figures.