Addition of a manganese treatment at the drinking water production plant
Federal contribution
$1.2M
$1,154,229
Federal share40%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Joseph-du-Lac
- Construction start
- Jul 22, 2020(actual)
- Construction end
- Dec 20, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 12, 2020
- Construction end12 months lateforecast Dec 31, 2022
Also in Saint-Joseph-du-Lac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56540 in the federal list. How to read these figures.