Addition of a manganese treatment at the drinking water production plant

Saint-Joseph-du-Lac, Quebec

completeDrinking WaterGIS
Federal contribution
$1.2M
$1,154,229
Federal share40%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Joseph-du-Lac
Construction start
Jul 22, 2020(actual)
Construction end
Dec 20, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 12, 2020
  • Construction end12 months lateforecast Dec 31, 2022