Back to projects

Water Systems Upgrades

Lambton, Quebec

completeWastewaterGIS
Federal contribution
$369,070
Federal share40%

of $922.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Lambton
Construction start
Jul 5, 2021(actual)
Construction end
Sep 30, 2021(actual)

Also in Lambton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56545 in the federal list. How to read these figures.