Water Systems Upgrades
Federal contribution
$628,459
Federal share40%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Marieville
- Construction start
- Jun 4, 2020(actual)
- Construction end
- Jun 30, 2021(actual)
Also in Marieville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56588 in the federal list. How to read these figures.