Siksika - Arthur A. Youngman WTP Flood Mitigation Raw Water Wells

Siksika Nation, Alberta

completeWastewaterGIS
Federal contribution
$1.6M
$1,575,000
Federal share75%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 26, 2020
2021202220232024
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Siksika Nation
Construction start
Nov 20, 2020(actual)
Construction end
Dec 1, 2023(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Dec 30, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56629 in the federal list. How to read these figures.