Back to projects

Town of Sexsmith – Regional Flood Mitigation Works

Sexsmith, Alberta

completeDisaster MitigationGIS
Federal contribution
$1.4M
$1,357,624
Federal share40%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2020
20212022
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Sexsmith
Construction start
Jul 18, 2022(actual)
Construction end
Nov 2, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 15, 2022
  • Construction end8 months earlyforecast Jun 30, 2023

Also in Sexsmith