City of Brooks Sanitary Wastewater Replacement and Hort Lift Station Connection
Federal contribution
$1.3M
$1,332,400
Federal share40%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2020
2021
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Brooks
- Construction start
- Oct 19, 2020(actual)
- Construction end
- Oct 8, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2020
- Construction end3 weeks lateforecast Sep 15, 2021
Also in Brooks
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56656 in the federal list. How to read these figures.