Town of Provost - Water Treatment Plant Upgrades
Federal contribution
$89,413
Federal share40%
of $223.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2020
2021
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Provost
- Construction start
- Aug 3, 2021(actual)
- Construction end
- Oct 31, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast May 10, 2021
Also in Provost
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56661 in the federal list. How to read these figures.