Buffalo Lake Metis Settlement - Water Treatment Plant Upgrade
Buffalo Lake Metis Settlement, Alberta
Federal contribution
$465,450
Federal share75%
of $620.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2020
202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Buffalo Lake Metis Settlement
- Construction start
- Jun 13, 2022(actual)
- Construction end
- Sep 19, 2023(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56662 in the federal list. How to read these figures.