Sylvan Lake Regional Wastewater System - Completion of North Shore Line (Stage 4 Systems)
Federal contribution
$1.5M
$1,516,384
Federal share40%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 25, 2020
20212022
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Sylvan Lake Regional Wastewater Commission
- Construction start
- Jun 15, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 17, 2021
- Construction end4 weeks lateforecast Mar 3, 2022
Also in Sylvan Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56664 in the federal list. How to read these figures.