Municipal District of Lesser Slave River #124 - Smith Lagoon Re-Lining
Lesser Slave River No. 124, Alberta
Federal contribution
$820,725
Federal share40%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2020
20212022
Built
Approved 7 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipal District of Lesser Slave River No. 124
- Construction start
- Jun 24, 2021(actual)
- Construction end
- Sep 16, 2022(actual)
Against the original forecast
- Construction end8 months lateforecast Jan 3, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56667 in the federal list. How to read these figures.