Back to projects

Municipal District of Lesser Slave River #124 - Smith Lagoon Re-Lining

Lesser Slave River No. 124, Alberta

completeWastewaterGIS
Federal contribution
$820,725
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2020
20212022
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 24, 2021(actual)
Construction end
Sep 16, 2022(actual)

Against the original forecast

  • Construction end8 months lateforecast Jan 3, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56667 in the federal list. How to read these figures.