Clairmont Regional Lift Station
Grande Prairie No. 1 (County), Alberta
Federal contribution
$9.2M
$9,201,937
Federal share40%
of $23.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- County of Grande Prairie No. 1
- Construction start
- Oct 16, 2020(actual)
- Construction end
- Dec 22, 2022(actual)
Against the original forecast
- Construction end5 weeks lateforecast Nov 15, 2022