Clairmont Regional Lift Station

Grande Prairie No. 1 (County), Alberta

completeWastewaterGIS
Federal contribution
$9.2M
$9,201,937
Federal share40%

of $23.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Oct 16, 2020(actual)
Construction end
Dec 22, 2022(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Nov 15, 2022

Also in Grande Prairie No. 1 (County)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56676 in the federal list. How to read these figures.