Frank Wastewater Plant Upgrade

Crowsnest Pass, Alberta

completeWastewaterGIS
Federal contribution
$7.8M
$7,800,000
Federal share40%

of $19.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 26, 2020
202120222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Mar 29, 2021(actual)
Construction end
Jul 26, 2023(actual)

Against the original forecast

  • Construction end8 weeks lateforecast May 31, 2023

Also in Crowsnest Pass

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56679 in the federal list. How to read these figures.