Frank Wastewater Plant Upgrade
Federal contribution
$7.8M
$7,800,000
Federal share40%
of $19.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2020
202120222023
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Crowsnest Pass
- Construction start
- Mar 29, 2021(actual)
- Construction end
- Jul 26, 2023(actual)
Against the original forecast
- Construction end8 weeks lateforecast May 31, 2023