Highway 12/21 Regional Water Services Commission - Completion of Phases 6 and 7 of the Regional Water Transmission Line

Camrose County, Alberta

completeDrinking WaterGIS
Federal contribution
$3.4M
$3,409,120
Federal share40%

of $8.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 11, 2020
202120222023
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 4, 2021(actual)
Construction end
Oct 19, 2023(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 15, 2021
  • Construction end5 months lateforecast May 31, 2023