Highway 12/21 Regional Water Services Commission - Completion of Phases 6 and 7 of the Regional Water Transmission Line
Federal contribution
$3.4M
$3,409,120
Federal share40%
of $8.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2020
202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Highway 12/21 Regional Water Services Commission
- Construction start
- Jul 4, 2021(actual)
- Construction end
- Oct 19, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 15, 2021
- Construction end5 months lateforecast May 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56680 in the federal list. How to read these figures.