Town of Trochu Lagoon Expansion

Trochu, Alberta

completeWastewaterGIS
Federal contribution
$1.1M
$1,081,285
Federal share40%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
2021
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Trochu
Construction start
Aug 4, 2020(actual)
Construction end
Jan 15, 2021(actual)

Against the original forecast

  • Construction end5 months earlyforecast Jun 30, 2021