Sewer System Extension on Saint-Philippe and Matte Streets
Federal contribution
$193,200
Federal share40%
of $483.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
20212022
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Alban
- Construction start
- Jul 7, 2020(actual)
- Construction end
- Nov 15, 2022(actual)
Against the original forecast
- Construction start23 months earlyforecast Jun 6, 2022
- Construction end2 weeks lateforecast Oct 31, 2022
Also in Saint-Alban
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56692 in the federal list. How to read these figures.