Water Systems Upgrades

Témiscouata-sur-le-Lac, Quebec

completeWastewaterGIS
Federal contribution
$2.0M
$1,993,231
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 17, 2021(actual)
Construction end
Oct 27, 2021(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 17, 2021
  • Construction end4 weeks lateforecast Sep 30, 2021

Also in Témiscouata-sur-le-Lac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56695 in the federal list. How to read these figures.