Water Systems Upgrades

Joliette, Quebec

completeWastewaterGIS
Federal contribution
$2.0M
$1,998,755
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 17, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Joliette
Construction start
May 17, 2021(actual)
Construction end
Jan 20, 2022(actual)

Against the original forecast

  • Construction end5 months earlyforecast Jun 24, 2022