Back to projects

Water Systems Upgrades

Lac-Mégantic, Quebec

completeWastewaterGIS
Federal contribution
$418,608
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Lac-Mégantic
Construction start
Aug 3, 2020(actual)
Construction end
Oct 30, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 18, 2020
  • Construction end2 months lateforecast Aug 28, 2020

Also in Lac-Mégantic