Cedar Dunes Shoreline Restoration

West Point, Prince Edward Island

completeDisaster MitigationGIS
Federal contribution
$700,000
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2020
20212022
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Nov 4, 2020(actual)
Construction end
Mar 9, 2022(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Mar 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56735 in the federal list. How to read these figures.