completeDrinking WaterGIS
Federal contribution
$957,893
Federal share40%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Damase
Construction start
Apr 21, 2021(actual)
Construction end
Oct 27, 2022(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 30, 2022