Back to projects

Village of Kingston - Library Renovation

Kingston, Nova Scotia

completeCultureRNIS
Federal contribution
$200,000
Federal share40%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
20212022
Built

Approved 11 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Kingston
Construction start
Jul 8, 2020(actual)
Construction end
Jun 20, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2020
  • Construction end6 months lateforecast Dec 31, 2021

Also in Kingston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56776 in the federal list. How to read these figures.