Upgrade Water and Sewer on Pike's Road

Lewin's Cove, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$137,711
Federal share40%

of $344.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
2021
Built

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Lewin's Cove
Construction start
Oct 5, 2020(actual)
Construction end
Jul 3, 2021(actual)

Against the original forecast

  • Construction end9 months earlyforecast Mar 31, 2022

Also in Lewin's Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56784 in the federal list. How to read these figures.