Back to projects

Pardy's Point Water and Sewer Upgrades

Garnish, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$241,366
Federal share40%

of $603.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Garnish
Construction start
Jul 12, 2021(actual)
Construction end
Nov 5, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast May 3, 2021
  • Construction end4 months lateforecast Jun 30, 2022

Also in Garnish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56790 in the federal list. How to read these figures.