Berm/Intake and Pumphouse Upgrades
St. Pauls, Newfoundland and Labrador
Federal contribution
$131,291
Federal share36%
of $362.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- St. Pauls
- Construction start
- Jul 26, 2021(actual)
- Construction end
- Nov 5, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 17, 2021
- Construction end3 months lateforecast Jul 31, 2021
Also in St. Pauls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56801 in the federal list. How to read these figures.