Water System Upgrade
Federal contribution
$2.0M
$1,999,200
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 17, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Jacques
- Construction start
- May 17, 2021(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 2, 2021
- Construction end6 months lateforecast Jun 30, 2022
Also in Saint-Jacques
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56807 in the federal list. How to read these figures.