Water System Upgrades

Grenville-sur-la-Rouge, Quebec

completeDrinking WaterGIS
Federal contribution
$997,820
Federal share40%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Grenville-sur-la-Rouge
Construction start
Jul 12, 2021(actual)
Construction end
Oct 14, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 10, 2021
  • Construction end5 months lateforecast May 20, 2022