Bedlam Pond Water Supply System
Colliers, Newfoundland and Labrador
Federal contribution
$129,452
Federal share40%
of $323.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 14, 2021
20212022
Built
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Colliers
- Construction start
- Jun 20, 2021(actual)
- Construction end
- Dec 21, 2021(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 15, 2021
- Construction end7 months earlyforecast Jul 30, 2022
Also in Colliers
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56819 in the federal list. How to read these figures.