Main Street Upgrades – Water and Sewer

Beachside, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$149,512
Federal share37%

of $405.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
202120222023
Built

Approved 11 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Beachside
Construction start
Aug 26, 2021(actual)
Construction end
Jul 21, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2021
  • Construction end3 weeks lateforecast Jun 30, 2023