Rowsell’s Point Road and Port Anson Road

Port Anson, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$270,885
Federal share37%

of $728.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
2021
Built

Approved 8 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Port Anson
Construction start
Jul 19, 2021(actual)
Construction end
Sep 17, 2021(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 15, 2021
  • Construction end6 months earlyforecast Mar 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56825 in the federal list. How to read these figures.