Armour Stone Protection
Terrenceville, Newfoundland and Labrador
Federal contribution
$142,353
Federal share40%
of $355.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
20212022
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Terrenceville
- Construction start
- Jun 15, 2022(actual)
- Construction end
- Nov 4, 2022(actual)
Against the original forecast
- Construction end7 weeks lateforecast Sep 15, 2022