Installation of Septic System
Riverhead, Newfoundland and Labrador
Federal contribution
$23,623
Federal share39%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
2021
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Riverhead
- Construction start
- Jul 2, 2021(actual)
- Construction end
- Jul 15, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2021
- Construction end7 weeks lateforecast May 30, 2021