Back to projects

Installation of Septic System

Riverhead, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$23,623
Federal share39%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
2021
Built

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Riverhead
Construction start
Jul 2, 2021(actual)
Construction end
Jul 15, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2021
  • Construction end7 weeks lateforecast May 30, 2021

Also in Riverhead

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56831 in the federal list. How to read these figures.