Back to projects

Sanitary Sewer Outfall Replacement - Welsh's Hill

Heart's Delight-Islington, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$144,323
Federal share40%

of $360.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 5, 2021(actual)
Construction end
Jul 11, 2022(actual)

Against the original forecast

  • Construction end7 months lateforecast Nov 29, 2021

Also in Heart's Delight-Islington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56845 in the federal list. How to read these figures.