Chlorine Booster System & Distribution Upgrades
Salvage, Newfoundland and Labrador
Federal contribution
$155,873
Federal share37%
of $420.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
202120222023
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Eastport
- Construction start
- Sep 5, 2022(actual)
- Construction end
- Apr 11, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 15, 2022
- Construction end4 months lateforecast Dec 15, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56846 in the federal list. How to read these figures.