Back to projects

Chlorine Booster System & Distribution Upgrades

Salvage, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$155,873
Federal share37%

of $420.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
202120222023
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Eastport
Construction start
Sep 5, 2022(actual)
Construction end
Apr 11, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2022
  • Construction end4 months lateforecast Dec 15, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56846 in the federal list. How to read these figures.