Water and Sewer Upgrades - Shea Avenue - Glenwood
Glenwood, Newfoundland and Labrador
Federal contribution
$102,907
Federal share39%
of $264.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2021
2021
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Glenwood
- Construction start
- May 26, 2021(actual)
- Construction end
- Sep 30, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2021
- Construction end3 months earlyforecast Dec 24, 2021
Also in Glenwood