Water Main Extension
Burlington, Newfoundland and Labrador
Federal contribution
$127,881
Federal share40%
of $319.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2021
2021
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Burlington
- Construction start
- Aug 5, 2021(actual)
- Construction end
- Sep 30, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2021
- Construction end3 months earlyforecast Dec 27, 2021