Back to projects

Water Main Extension

Burlington, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$127,881
Federal share40%

of $319.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
2021
Built

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Burlington
Construction start
Aug 5, 2021(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2021
  • Construction end3 months earlyforecast Dec 27, 2021

Also in Burlington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56859 in the federal list. How to read these figures.