Long Pond Park & Trail Development

Bay Bulls, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$143,745
Federal share33%

of $431.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
2021202220232024
Built

Approved 3.7 years before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Bay Bulls
Construction start
Sep 21, 2021(actual)
Construction end
Jun 15, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2021
  • Construction end3 weeks lateforecast May 22, 2022