Long Pond Park & Trail Development
Bay Bulls, Newfoundland and Labrador
Federal contribution
$143,745
Federal share33%
of $431.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
2021202220232024
Built
Approved 3.7 years before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Bay Bulls
- Construction start
- Sep 21, 2021(actual)
- Construction end
- Jun 15, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2021
- Construction end3 weeks lateforecast May 22, 2022
Also in Bay Bulls