Road Resurfacing - North West River
North West River, Newfoundland and Labrador
Federal contribution
$44,413
Federal share33%
of $133.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 3, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- North West River
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Oct 20, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2021
- Construction end7 weeks lateforecast Sep 1, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56876 in the federal list. How to read these figures.